"Increasing the localization level of beams for drive axles of commercial vehicles" requested by KamLitKZ LLP (3rd deal)
«Organization of tire production in Saran, Karaganda region" on an application of KamaTyresKZ LLP
Projects financed in support of manufacturing industry
Industry: Manufacturing, "Production of main gears for drive axles"
In 2023, the Fund started financing the "Increasing the localization level of beams for drive axles of commercial vehicles" project requested by KamLitKZ LLP for a total amount of 59,920,030 thousand tenge, including a financing amount of 55,000,000 thousand tenge to create a new production by KamLitKZ LLP. The project's goal is to develop, by 2025, production sites for the mechanical processing of beams for drive axles of commercial vehicles in the automotive sector of the Republic of Kazakhstan.
The project plans to produce an average of 101 thousand units of beams for drive axles of commercial vehicles with a planned average annual revenue of about 6-7 billion tenge, and create/preserve about 100 jobs. The plant's commissioning is planned for the 3rd quarter of 2025.
Industry: Manufacturing industry, Manufacture of rubber tires and chambers; restoration of rubber tires.
In 2023 the Fund continued financing for an amount of 66 422 400.00 thousand tenge of the total amount of 78 144 000,00 thousand tenge for the “Organization of the production of tires in Saran, Karaganda region” project on an application of KamaTyresKZ LLP - a joint venture of Tatneft PJSC and AllurAuto, to create a new production. The leasing transaction will allow to purchase modern automated equipment for the production of tires for the plant in Saran. The company is currently operating in Saran.39 The attraction of financing within the framework of the state programs of the Republic of Kazakhstan is one of the measures of the state support of the project by the Government of the Republic of Kazakhstan. The project provides the purchase of equipment from leading world manufacturers, including MESNAC, KONŠTRUKTA, Vipo, PROZAX, Comerio Ercole, NAKATA ENGINEERING, etc. The level of technology will allow the automation of most production processes, but at the same time the enterprise will provide work for more than 1,116 people, and its creation will require more than 2,000 builders. The production of the new plant with a capacity of 3 million passenger, light-cargo tires and 0.5 million all-metal-cord truck tires per year will be directed to the initial set-up of cars produced in Kazakhstan, the secondary market, as well as to export to the CIS countries. On April 5, 2021, a ceremony was held to begin construction of the plant. At present, the construction site of the future plant is being used for the installation of foundations, reinforced concrete, and metal structures of the main production building. The launch of production, which will create more than a thousand jobs, is planned for the first quarter of 2024.
Construction of a Knitted Socks Factory with a capacity of 24.84 million pairs per year in Ontustik SEZ, Shymkent by Balabi Textile LLP
Construction of a Wool Primary Processing Workshop and Non-Woven Materials Production in Aktobe by KazFeltec LLP
Non-Woven Geotextile Fabric Plant in SEZ NINT by INTAGO-KAZAKHSTAN LLP
Acquisition of Technological Equipment for Cardboard Packaging for Liquid Products (Pure-Pak) by Kazpoligraph LLP (3rd deal)
Industry: Manufacturing, "Production of knitted and crocheted hosiery products"
In 2023, funding was approved and initiated for a total of 6,586,840 thousand tenge, with a financing amount of 3,674,245 thousand tenge. The project aims to organize the production of high-quality knitted products – socks, with a capacity of 49.68 million pairs per year. The project will create 368 new jobs, with the factory's operation beginning in the 3rd quarter of 2024.
Industry: Manufacturing, "Production of Nonwoven Textile Articles, Except Apparel"
In 2023, funding was approved and initiated for a total of 4,264,044 thousand tenge, including a f inancing amount of 3,334,524 thousand tenge. The project's goal is to establish a modern high-tech enterprise for the production of natural non-woven materials made from animal fibers (sheep wool). The project will create 40 new jobs and is expected to produce 2,112 tons of finished products annually, with 1,478 tons for the domestic market and 634 tons for export.
Industry: Manufacturing, "Production of Nonwoven Textile Articles, Except Apparel"
Funding was approved and initiated in 2023 for a total of 726,451 thousand tenge, including a financing amount of 594,729 thousand tenge. The project aims to establish a modern export-oriented enterprise for the production of non-woven geosynthetic materials. It will create 36 new jobs, with an annual production volume of 15,120,000 square meters, or 3,600 tons of non-woven geotextile fabric.
Industry: Manufacturing, "Production of Paper and Cardboard Articles".
Funding was approved and initiated in 2023 for a total of 5,443,374 thousand tenge, including a f inancing amount of 3,760,728 thousand tenge. The project aims to expand the existing production and assortment of cardboard packaging for liquid products (Pure-Pak), increase annual production volumes to 327 million units, and create 16 new jobs.
Modernization of Pavlodar Pipe Rolling Plant by Pavlodar Pipe Rolling Plant LLP
"Construction of the first stage, the first start-up complex, four ore-thermal furnaces" at the request of QARAGANDY POWER SILICON LLP
Industry: Manufacturing, "Production of Tubes, Pipes, Hollow Profiles, and Steel Fittings".
In 2023, the Fund approved and initiated funding for the project in the amount of 438,651,680 tenge, of which the f inancing amount is 372,853,928 tenge. The project has been fully funded. The project plans to produce up to 15,120 tons of pipes and 454 tons of wire annually. The operation is scheduled to start in the second half of 2024.
The implementation of the project will allow:
⮚ Expansion of the range of steel pipes by producing round electric-welded steel pipes with diameters from 40 to 219 mm and square profile pipes with diameters from 40 to 100 mm;
⮚ Increasing the range of products produced by manufacturing steel wire, which will enable waste-free production; ⮚ Optimizing the technological process.
Industry: Manufacturing, "Production of iron, steel, and ferroalloys".
In 2023, the Fund approved and initiated funding for the construction of the first stage, the first startup complex, four ore-thermal furnaces in the Karaganda region for a total amount of 28,682,533.33 thousand tenge, where the Fund's financing amount is 20,000,000.00 thousand tenge. The project aims to organize the production of ferroalloys in the Karaganda region, in the Bukhar-Zhyrau district, Zelenobalkovsky rural district, Doskey village, with a production capacity of up to 180 thousand tons of products per year. The plant's commissioning is planned for the 3rd quarter of 2024.
"Complex of building materials production - Autoclaved Aerated Concrete" requested by TK Gazoblok LLP
Industry: Manufacturing, Production of wall blocks.
In 2023, the Fund approved and initiated funding for the "Complex of building materials production - Autoclaved Aerated Concrete" project for a total amount of 3,506,135 thousand tenge, where the Fund's financing amounted to 2,950,000 thousand tenge. The project aims to organize the production of autoclaved aerated concrete in the Almaty region, with a production capacity of up to 75 thousand cubic meters of products per year. The plant's commissioning is planned for 2024.
The implementation of the project will provide the region with quality building materials, create new jobs, and increase tax revenues to the budget.
"Establishment of Steel Water Heating Gas Boiler Production in Karaganda" requested by TERMA BOILER LLP
"Organization of Production by Small-Node Assembly Method of LADA, KIA Brand Cars in the Territory of the Republic of Kazakhstan in the Industrial Zone in Kostanay Region" requested by SaryarkaAvtoProm LLP (3rd deal)
"Organization of a Mechanical Processing Site" requested by Aliot-service LLP
Industry: Manufacturing, Production of Radiators and Central Heating Boilers.
In 2023, funding for the project "Establishment of Steel Water Heating Gas Boilers in Karaganda" was approved and commenced for a total amount of 211,351.7 thousand tenge, including a financing amount of 128,102.6 thousand tenge. The project aims to create a new production of steel water heating gas boilers, and to create new jobs. The projected capacity of the f irst phase of the plant is 110 boilers per year.
Industry: Manufacturing, Engineering.
In 2023, the "Organization of Production by Small-Node Assembly Method of LADA, KIA Brand Cars in the Territory of the Republic of Kazakhstan in the Industrial Zone in Kostanay region" project was approved and funding began for a total amount of 10,989,641.2 thousand tenge, including a financing amount of 7,692,748.9 thousand tenge. The aim of this project is to increase the localization of car production on the territory of the Republic of Kazakhstan through the introduction of CKD small-node assembly production for LADA, and KIA brand cars. The operation was launched on December 25, 2023. The project implementation will result in the creation of up to 600 new jobs and additional tax payments to the budget.
Industry: Manufacturing, Engineering.
In 2023, "Organization of a Mechanical Processing Site" project was approved and funding began for a total amount of 5,608,635.5 thousand tenge, including a financing amount of 3,954,008.70 thousand tenge. The goal of this project is to set up a mechanical processing site within the premises of the forge-bandage complex. The operation is planned to commence in the 4th quarter of 2024.